Construction Overview

Building with Speed and Precision

At Korndoerfer Homes, we take pride in consistently achieving fast cycle times by delivering new homes in seven months or less. The timeline is adjusted to approximately eight months if you are adding a finished basement. Our streamlined process and commitment to efficiency allow us to deliver high-quality homes with speed and precision, without compromising on quality or attention to detail.

    1

    Month 1

    Laying the Foundation

    During the first month, we excavate your home and pour the footings and foundation walls. Afterward, we allow the foundation to properly cure while obtaining the required foundation inspections and completing the backfill process.

      2

      Month 2

      Framing and Rough-Ins

      This is when you really start to see your home take shape! Our carpenters frame the structure, and we install windows and doors. Simultaneously, we begin the plumbing, heating, and electrical rough-ins.

        3

        Month 3

        Roofing & Mechanical Installation

        In the third month, we finish the plumbing, heating, and electrical rough-ins and install the roof shingles. The fireplace is installed, and we pour the garage and basement slabs. At this point, we conduct inspections of the plumbing, electrical work, and rough framing. Your Field Superintendent will walk you through your new home so you can inspect the mechanicals before we begin installing drywall.

          4

          Month 4

          Insulation & Interior Finishing

          Next, we insulate the walls and have them inspected. The furnace is typically installed during this phase, though it may be installed later in warmer months. We then drywall, finish, texture, and paint the walls.

            5

            Month 5

            Interior Detailing

            As we move into the fifth month, the focus shifts to interior details. We install ceramic tile, vinyl flooring, and trim work such as doors, stairs, molding, and baseboards. Cabinets are installed, countertops are ordered, and the fireplace mantel is set.

              6

              Month 6

              Final Details

              Your home is almost ready! In the final month, we finish painting and staining, install countertops, light fixtures, mirrors, shower doors, bath accessories, and complete the flooring installation.

                7

                Month 7

                Finishing Touches & Moving Day

                Sitework and exterior painting are completed, and we schedule final home inspections. Your Field Superintendent will conduct a home orientation which consists of showing you all the systems in the home. After a thorough cleaning, we’ll conduct a walkthrough and document any punch list items. The finishing touches are completed and then it’s the moment you’ve been waiting for—moving day!

                  Questions?
                  Ask Ryan Today!

                  Start Planning Your New Home

                  Call Icon
                  Call Us
                  (262) 884-9551
                  Request Information
                  Virtual Appointment Icon
                  Book A Time To Chat
                  Home Tour Icon
                  Schedule a Home Tour
                    • Korndoerfer Homes
                    • 175 N Corporate Drive, Suite 130
                    • Brookfield, WI 53045
                    • (262) 884-9551
                    icon equal housing

                    We collect personally identifiable information, like names, postal addresses, email addresses, phone numbers, etc., only when voluntarily submitted by our visitors. Learn more on our Privacy Policy page.

                    Ryan Schultz

                    Questions?Ask Ryan